Shop Fit-Out - High Street Kensington

Project Details

Location:
Kensington
Project Type:
Commercial
Value:
£100,000
Completion:
December 2021

Project Overview

Kensington High Street is considered amongst many as being one of London’s most popular and exclusive shopping streets, with swanky shops serving an affluent area enjoyed equally by both residents and tourists.

The prestigious area and surroundings meant work must be delicate, in addition to the complex and large-scale nature of the project meant this fit-out was more challenging (on paper) than others.

Our sister company Yasmeen Property Services was the main contractor on this project and all the joinery works was done by us, Yasmeen Joinery.

A variety of joinery products were required for the fit-out, but the awkward space distribution and floor plan required precise measurements, drawings, and manufacturing, never a problem with Yasmeen Joinery.

The Shop Interior design contained a lot of glass and marble and we worked alongside our suppliers to source, manufacture and install high quality glass and marble, and all this was coordinated internally with the client having one point of contact only, the project manager.

What Was Built

JOINERY CUPBOARDS

We manufactured a large number of cupboards for the client to store products and stock, complete with soft-closing doors and shelving inside.

We sourced high quality marble and integrated it in the worktop to ensure a great looking and functioning piece.

Oak-clad serving counter with white marble worktop and glass-topped displayMarble-topped counter with concealed cupboards against oak-clad shop wall

JOINERY STORAGE

The client’s brief described the need to create and increase storage space. After surveying the shop to indentify all the unused (and underused) spaces, we then alleviated their space problem through a bespoke storage solution in the form of custom-made cupboards that utilised every CM of available space and allowed the client to increase their overall storage capacity considerably.

We also made sure to cover the cabinets in the same wood cladding that we used throughout the shop to ensure a consistent design.

Joinery Shelving

We created bespoke frames for the shelving. The frames carry the same design as the shop and have built-in LED lighting.

Run of bespoke shelving bays framed by slatted oak panellingRecessed wall shelving in an oak frame with built-in LED strip lighting

DISPLAY JOINERY BEHIND TILL

The display piece behind the till is a major focus point and is considered the centrepiece of the shop. It a complex display unit that must offer the best in both form and function.

We created a unique and elegant piece that not only looks great, but doubles as storage as well. We also included built-in LED lighting and shelving made from high quality glass.

Finally, we cut-out double sockets in the unit to ensure maximum convenience.

Curved oak-slat ceiling above an LED-lit display wall behind the tillDetail of curved oak ribs and concealed LED lighting on the ceiling

BAKERY JOINERY

This area is for displaying the client’s bakery products. We created a bespoke storage and display solution that takes into consideration the awkward floor space and ensures the client’s products are well displayed and every CM of space is utilised.

We also added built-in LED lighting all around so that the client’s products are well lit, and we added bottom glass partitioning.

Circular Shelving

We manufactured a number of these circular shelving units that are located around the shop.

Bespoke oak bakery display unit with stepped shelving and glass partitionsCorner oak shelving bays with LED strips and glass-fronted lower unitsFreestanding circular oak display unit with tiered round shelves

WALL CLADDING

We installed wooden cladding around most walls in the shop. The cladding along with our bespoke joinery created a great design that consistently carries out throughout.

Slatted oak wall cladding above a stairwell with glass balustradeOak-slat clad wall running alongside a staircase with glass balustrade

Our Process

How we do it

From your initial concept to completion, we aim to deliver in about 6–8 weeks, this is our tried and tested process:

  1. 01. Initial Consultation

    Here is where we understand your vision and requirements. Sometimes, translating the vision in your head to an idea on paper is the hardest step in the process, but we are good at it.

  2. 02. Conceptual Designs & Quote

    We put all gathered information, sketches, pictures, measurements and notes to good use and design initial concepts and sketches.

  3. 03. Technical Designs

    Once the quote and initial concepts are approved, we expand on them with detailed 3D technical designs covering all aspects and details of the project, ensuring a perfect fit before we even begin.

  4. 04. Manufacturing

    Our skilled team will expertly craft your bespoke product from our local, state-of-the-art workshop located in Park Royal, London (NW10).

  5. 05. Installation

    At the agreed date and once the manufacturing and all the associated quality checks are completed, we will coordinate with you a convenient time for delivery or installation.

  6. 06. Handover

    The project manager will inspect the completed project with you. Once we’re happy with the item and the installation, our work is finally done and the handover is complete.

Why choose us

Yasmeen Joinery craftsman finishing a piece at the workbench

No person or company is perfect, and if a problem should occur during the job (regardless of who is to blame), we respond immediately and work with you to find the best resolution. Our company is built on repeat business and referrals, so we make sure we deliver a quality service where customer satisfaction is our top priority.